In accordance with the RF Government Resolution dd. February 16, 2008 of No. 87 "About project documentation chapters structure and requirements to their contents" our company at the Project documentation stage develops the following project chapters:
- POS (Construction management plan);
- POD (Dismantling management plan);
- PPR (Works execution plan).
Structure of the Construction management plan:
construction general layout for the preparatory period of construction;
construction general layout for the main period of construction;
sections, process schemes;
schedule of works;
explanatory note (containing calculation of the electric power, water, people, mechanisms, construction duration).
Structure of the Dismantling management plan:
- scheme of structures demolition (aligned with the soil survey);
- sections and process schemes of dismantling demolition of a structure;
- explanatory note.
Structure of the Works execution plan:
PPR for the preparatory period:
- horizontal and vertical schemes of the crane alocation for the preparatory period works;
- roping schemes;
- process schemes;
- explanatory note.
PPR on a tower crane (the truck crane, truck-mounted concrete pump):
- horizontal and vertical schemes of a tower crane (truck crane):
- collaboration of mechanisms;
- roping schemes;
- explanatory note.
PPR on concreting of the structures:
- an arrangement of working seams when concreting basement plate, overlapping plates;
- process scheme of concreting of overlappings;
- schematic diagrams of the walls, columns timbering;
- schemes of the organization of works on installation of metal frameworks of columns;
- regulations on control of durability of concrete when concreting designs;
- quality control tables;
- planned schedule of works;
- explanatory note.
PPR on laying of communications.
PPR on production of the earthworks (grooving, "wall in trench", piles):
- horizontal and vertical schemes of the excavator (drilling rig) allocation;
- process schemes;
- explanatory note.
PPR on installation of the building timber (cradles, portable platforms):
- horizontal and vertical schemes of the building timber, fastening joints of the timber to the building structures, the installation dismantle scheme;
- schemes of the timber installations on the building facades with places of their fastening;
- explanatory note.
PPR on installation of lifts:
- horizontal and vertical schemes of the lifts;
- collaboration of mechanisms;
- explanatory note.
PPR on internal furnish of a building.